STATE ROUTE 170 EXPANSION PROJECT
A. Demolition: December 2005/Janurary 2006
Depended upon asbestos removal and letting contract.
* Completed February 2-3, 2006; 2 of 5 businesses affected are back open, Bowyer’s remained open and moved part of their operation to East Liverpool Road, Bruster’s planning to re-open on same lot in different spot, Bruno’s Pizza moved operations temporarily to Dunham’s Plaza and plans to rebuild a stand alone operation after construction is done.
B. Bid project in February to begin end of March
C. Construction March thru October
1. Mid-March begin on Sprucevale from
2. Early April replace and enlarge
culvert cross-over pipe under State Route 170 between
3. Closer toward summer, begin working on State Route 170 on side closest to school first, then the opposite side. Traffic maintained both directions.
Phase II. 2007
A. R/W completed by September of 2006, 3 business affected for relocation are Quick Lube, Quaker Pool & Spa, Calcutta Auto Parts.
B. Construction to begin mid-March 2007; access to businesses to remain open, traffic to be maintained in both directions throughout.
1. Begin on
N side
2. Move to opposite side and finish the remaining 3 lanes
3. Clean-up and finish intersections
4. Complete
S side of
Add $1 million for engineering and total project cost equals $14.5 million.
Press the BACK button on your browser to return to the Chamber main web page. - Thank you.